The Tirana–Durrës–Rinas railway: new deadlines and what it means for property along the line

Electrification is funded, the loan ratified and the state is seeking an operator with trains. Service is due at the end of 2027. What it means near the stations.

By 6 min read

The Tirana–Durrës–Rinas railway: new deadlines and what it means for property along the line

A train between Tirana and Durrës has been promised many times. This summer the project took some concrete steps: in July a winner was announced for the electrification, in August parliament ratified the EBRD loan, and the government is looking for a private operator that will also bring the trains. The official date for starting passenger services is now the fourth quarter of 2027. For anyone who owns, or is thinking of buying, property in Kashar, Vorë, Sukth, Shkozet or near Rinas airport, this line could change how property value is worked out. Here is what has been decided, what is still uncertain and how to read it.

Cover photo: Mateusz Wysocki / Unsplash

What was decided this summer

Tirana–Durrës–Rinas railway, 2026 milestones
  1. Ministry opens the call for a service operatorThe operator must also supply the trains
  2. Government: line fully operational in 2027Statement by deputy minister Edona Bilali (ATSH)
  3. Parliamentary committee approves the electrification loanAn Italian company won with a €22m bid, according to Lexo
  4. Deadline for operators' expressions of interestAccording to Monitor
  5. EBRD loan ratified€11.62m, with a 50% EU grant
  6. Planned start of electrification worksAccording to deputy minister Enkelejda Muçaj
  7. Passenger services beginFourth quarter of 2027, according to Monitor

The call for an operator was published by the Ministry of Infrastructure and Energy on 27 May 2026, and companies had until 26 July to express interest; the tender is expected to open in the fourth quarter of 2026 (Monitor, 9 June 2026). The operator will sign a 10–15 year contract, be paid per kilometre run, and must supply 4 electric trains (6 including reserves). The risk on ticket revenue stays with the state.

For the electrification, the winning contract is worth about €22 million, half of it financed by an EU grant, and includes two electrical substations, in Tirana and Durrës (Lexo, 3 July 2026). The €11.62 million EBRD loan, ratified in August, covers electrifying about 34.17 km of the Tirana–Durrës line and a new link to the airport (Zyrtare.net, 2 August 2026).

Tirana–Durrës by rail (Monitor)
37.9 km
Tirana–Rinas airport (Monitor)
15.4 km
Planned top speed (Top Channel)
120 km/h
Project cost so far, up from €69.7m in 2020 (ACQJ)
>€118m

How many trains there will be

According to Monitor, 44 Tirana–Durrës services (22 round trips) and 74 Tirana–Airport services (37 round trips) are planned on weekdays, about 1.1 million train-kilometres a year. Trains will be able to reach 120 km/h, but within Tirana speed will be limited to 70 km/h (Top Channel, 17 May 2026).

Planned weekday services
Tirana–Durrës442237.9 km
Tirana–Rinas airport743715.4 km
Source: Monitor, 9 June 2026

Why so late and so expensive

The construction contract was won in 2020 by the Italian company INC S.p.A. for €69.7 million, with a 2023 deadline. The project has now cost more than €118 million and over 97% of the core works are done (ACQJ, 12 May 2026). According to ACQJ, the delays were caused by expropriations, new seismic standards, rebuilt bridges and the addition of electrification. A new segment of about 4 km that will bring the station to the New Boulevard in Tirana has a €15.7 million tender with a 24-month deadline.

Photo: Sonny Sixteen / Pexels

The stations and the areas affected

According to Albanian Railways director Ergys Verdho, the project includes new stations in Kashar, Vorë, Tirana, Sukth and Shkozet, the rebuilding of the Durrës and Tirana stations, and a stop for students near Epoka University (Shqiptarja, 18 August 2025). The airport link branches off at Domje, where the new segment towards Rinas is being built (ATSH, 17 June 2026).

Stations on the Tirana–Durrës–Rinas line

Choose a place to see its details on the map.

Source: Shqiptarja (2025), ATSH and Monitor (2026); coordinates are approximate

Photo: Caleb Williams / Unsplash

What this means for property along the line

There is no data yet showing that prices near the stations have risen because of the train, and you should not assume they will rise automatically. But the experience of other European cities shows that a frequent, reliable service makes it easier to live away from the centre. With 22 round trips a day, Durrës and its suburbs could become a more realistic option for people who work in Tirana, and areas near Rinas could attract more demand for short-term rentals and logistics.

The risks are just as real: deadlines have slipped several times, the operator has not yet been chosen and the service will not start before the end of 2027. Buy for what the property is worth today, and treat the train as a possible bonus, not a guarantee.

Before you buy near a future station0 of 6
The official target according to Monitor is the fourth quarter of 2027. The government has said the line will be fully operational in 2027. Earlier deadlines (2023, 2025) were missed.
The sources we reviewed give the top speed (120 km/h, 70 km/h within Tirana) and the length (37.9 km), but no official journey time. We will have to wait for the operator's timetable.
According to Monitor, the planned extensions are Tirana–Hani i Hotit by 2030 and Durrës–Pogradec by 2035. These are long-term plans.
The private operator that wins the tender must supply the trains, while the state keeps the risk on ticket revenue.

See properties for sale in Durrës and value a property with our valuation tool.

Apartments for sale in DurrësSee all

Sources

Read more

Share the article

New articles by email

Guides on buying, renting and the property market in Albania, straight to your inbox.

One email when we publish a new article. You can unsubscribe at any time. Privacy

Comments

Log in to join the conversation.

No comments yet. Be the first to share your view.

List property